Lynn Vessels Construction, LLC
P.O. Box 1212 Sherman, Texas 75091-1212
March 31, 2014
NOTICE OF CONSTRUCTION
City of Gainesville 2010 SUMP Bond Bid Package ‘D, E, F’
Martin Luther King, MLK Blvd.
Start Date: April 1, 2014 End Date: January 26, 2015
This is to inform you that under a contract with City of Gainesville, our company will be reconstructing the street on or around your property.
Throughout the course of construction, we will be performing the following work:
• Install new water, sewer, and/or storm drain lines
• Excavation and Demolition of existing roadway
• Prepare, Stabilize and Compact subgrade material under new road
• Paving new concrete roadway
Construction will begin approximately 24 hrs. from the date of this notice.
There may be periods of time while paving the street, and installing the new driveways, that you have limited or no access to your driveway. We will do everything we can to minimize these instances.
We ask that you not park any vehicles in the roadway, and to reduce or eliminate any irrigation along the street. These steps will enable us to complete the reconstruction as quickly as possible.
If you have any questions about access, security, safety or any other issue, please call:
Steve Hightower (Contractor’s Superintendent) at (903) 814-4316 or
Chris Baugh (City of Gainesville Inspector) at (940) 668-4540
Evenings and weekends, please call (940) 902-1428.
PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL.